Question #: 374
Topic #: 1
[All PMP Questions]

During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams.
As a team facilitator, what should the project manager do to avoid this?

  • A. Reunite with the project team members affected and tell them not to reduce the team's capacity.
  • B. Hire a coach to help all project teams to improve their abilities to solve problems on their own.
  • C. Recommend to the project team members that they should improve their planning and make their stories smaller.
  • D. Identify the problem's root causes and define the ground rules with all project team members to minimize interferences.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lucky_Cindy
6 months, 3 weeks ago
Selected Answer: D
Definitely D
upvoted 1 times
...
victory108
9 months ago
Selected Answer: D
D. Identify the problem's root causes and define the ground rules with all project team members to minimize interferences
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...