Question #: 688
Topic #: 1
[All PMP Questions]

All project team members refer to the project manager for various decisions. This causes delays for some tasks. as the project manager is usually preoccupied in meetings throughout the day.

What should the project manager do to prevent these delays?

  • A. Meet with the team in 2 weeks to respond to all of the open tasks.
  • B. Review the Pareto diagram to identify the source of delays.
  • C. Delegate the decision-making authority of some tasks to the team.
  • D. Consolidate the decision-making authority to remain with the project manager.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
7 months ago
Selected Answer: C
C. Delegate the decision-making authority of some tasks to the team
upvoted 1 times
...
Scottxk1
8 months, 1 week ago
Selected Answer: C
I would choose C so that we can start to build some leadership qualities in your senior team members and work together instead of putting all the decisions on the PM.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago