All project team members refer to the project manager for various decisions. This causes delays for some tasks. as the project manager is usually preoccupied in meetings throughout the day.
What should the project manager do to prevent these delays?
A.
Meet with the team in 2 weeks to respond to all of the open tasks.
B.
Review the Pareto diagram to identify the source of delays.
C.
Delegate the decision-making authority of some tasks to the team.
D.
Consolidate the decision-making authority to remain with the project manager.
I would choose C so that we can start to build some leadership qualities in your senior team members and work together instead of putting all the decisions on the PM.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
7 months agoScottxk1
8 months, 1 week ago