A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product.
Which approach should the project manager take?
A.
Ask the team to raise blockers or impediments in daily meetings.
B.
Prioritize the tasks with high risks to reduce the number of iterations required.
C.
Ask the team to challenge the project estimations for a faster delivery.
D.
Prioritize deliverables based on business value and define frequent releases.
I choose D as this focuses the iterations only on the critical path items to achieve the main goal of the project and cut away the unnecessary features.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
7 months agoScottxk1
8 months, 1 week ago