A new government regulation has mandated that all team members will need to work remotely for the duration of the next iteration. This means backlog priority changes will need to be completed
What should the project manager do?
A.
Communicate the new regulation to the project sponsor during the next retrospective.
B.
Inform the product owner of the required change as soon as possible.
C.
Reprioritize the backlog and share it with the team as soon as possible.
D.
Ask the team facilitator to reprioritize the backlog based on the new regulation.
Direct communication with the product owner: The product owner, responsible for prioritizing the product backlog and aligning it with stakeholder needs, is the primary decision-maker when it comes to adjusting priorities in response to external factors like the new regulation.
Timely response and adaptation: Informing the product owner promptly ensures a rapid response to the situation and minimizes delays in adapting the backlog. This demonstrates initiative and proactiveness from the project manager.
Collaborative prioritization: The product owner, in consultation with the project manager and potentially other stakeholders, can engage in a collaborative and informed prioritization process to identify essential tasks that can be effectively executed remotely and adjust the backlog accordingly.
Ok who is a team facilitator? The Product owner is responsible for the backlog. They should be informed and they will make the necessary changes will the assistance of the PM. Who is a team facilitator?
B. Inform the product owner of the required change as soon as possible.
The product owner is responsible for managing and prioritizing the product backlog. When there are external factors like a new government regulation that might impact the prioritization or the work in the backlog, the product owner should be informed immediately. The product owner, with input from the team and stakeholders, can then make the necessary adjustments to the backlog to align with the new situation.
For the situation described where a new government regulation mandates remote work for the next iteration and backlog priority changes are required, the most appropriate course of action in an Agile context would be:
C. Reprioritize the backlog and share it with the team as soon as possible.
In Agile project management, it's essential to involve the Product Owner or Product Owner team in reprioritizing the backlog based on the new information. The project manager should collaborate with the Product Owner to make necessary adjustments and then communicate the changes to the development team. This ensures that the team works on the highest-priority items given the new circumstances while still aligning with stakeholder needs and business value.
The PM cannot and should not reprioritize the backlog. This is the responsibility of the Product Owner.
upvoted 2 times
...
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
khaleghi
Highly Voted 1 year, 3 months agochlaithem
Most Recent 11 months, 1 week agoHcwong
1 year agoChezQW
1 year, 1 month agoOnly12go
1 year, 1 month agovictory108
1 year, 2 months agoHcwong
1 year, 2 months agoRISHAB1234
1 year, 2 months agoChezQW
1 year, 1 month ago