An agile team is working on a two-week sprint to deliver business value. About one week after the sprint starts, the product owner realizes that a regulatory compliance requirement was missed. The product owner reminds the team that this requirement must be completed in the current sprint or the organization will face a penalty.
What should the project manager do to mitigate this risk?
Abdelmonm
Highly Voted 1 year, 3 months agoKim222
Most Recent 8 months, 1 week agotonybuivannghia
9 months, 1 week agoUppersquareCapital
11 months, 3 weeks agoLNX_RM_Admin
12 months agodebug91
1 year ago[Removed]
1 year, 2 months agohoomz
1 year, 2 months agochlaithem
1 year, 4 months agoDavid983
1 year, 6 months agoOnly12go
1 year, 6 months agoSumbo
1 year, 7 months agoAngelVii
1 year, 7 months agoSynikalDemon
1 year, 8 months agokhaleghi
1 year, 8 months ago