An agile team is working on a two-week sprint to deliver business value. About one week after the sprint starts, the product owner realizes that a regulatory compliance requirement was missed. The product owner reminds the team that this requirement must be completed in the current sprint or the organization will face a penalty.
What should the project manager do to mitigate this risk?
Abdelmonm
Highly Voted 1 year, 5 months ago8a6d137
1 week, 5 days agokkkyyyy
Most Recent 1 month ago21d5982
1 month, 1 week agoKim222
10 months agotonybuivannghia
11 months agoUppersquareCapital
1 year, 1 month agoLNX_RM_Admin
1 year, 1 month agodebug91
1 year, 1 month ago[Removed]
1 year, 4 months agohoomz
1 year, 4 months agochlaithem
1 year, 5 months agoDavid983
1 year, 8 months agoOnly12go
1 year, 8 months agoSumbo
1 year, 8 months agoAngelVii
1 year, 9 months agoSynikalDemon
1 year, 10 months agokhaleghi
1 year, 10 months ago