exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 857 discussion

Actual exam question from PMI's PMP
Question #: 857
Topic #: 1
[All PMP Questions]

A project manager is leading a project when a major crisis suddenly causes an economic downturn, which may threaten the project outcome. What should the project manager do?

  • A. Update the project charter and benefits management plan with the current realities.
  • B. Create a proposal suggesting that the project sponsor terminate the project.
  • C. Reallocate some project resources to other assignments in the organization.
  • D. Document the new risks in the project benefits management plan and risk management plan.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MidoGr
9 months ago
anyone choose D shoudnt take the exam, Document the new risks in risk register, not risk management plan
upvoted 1 times
...
buvana
1 year, 1 month ago
D is wrong - A is right. "Update the project charter and benefits management plan with the current realities." It involves updating essential project documents to reflect the changed circumstances comprehensively. This helps in ensuring that the project remains on track and continues to deliver value despite external challenges.
upvoted 2 times
...
YUCHAN2022
1 year, 3 months ago
Selected Answer: D
D is correct.
upvoted 1 times
...
Abdelmonm
1 year, 3 months ago
Selected Answer: D
In the face of a major crisis and economic downturn, it's important to assess and document the potential risks to the project. Documenting these risks in the project benefits management plan and risk management plan enables the project manager to understand the potential impacts on project outcomes and develop appropriate risk response strategies. It provides a basis for informed decision-making and proactive management of challenges that may arise due to the economic downturn.
upvoted 1 times
...
chlaithem
1 year, 4 months ago
Selected Answer: D
This option emphasizes comprehensive analysis and proactive risk management. By: Documenting new risks: Identifying and analyzing the potential impact of the economic downturn on the project's financial viability, timeline, and deliverables is crucial for informed decision-making. Updating the benefits management plan: Revising the expected benefits in light of the new context ensures stakeholder alignment and prioritizes projects with continued strategic value. Developing mitigation strategies: Proactively devising alternative approaches, cost-saving measures, or contingency plans demonstrates leadership and a commitment to project success despite the challenges.
upvoted 1 times
...
Waynelau
1 year, 4 months ago
Selected Answer: D
Should be D. "may threaten" mean not 100% negative, PM should not recommend to stop the project.
upvoted 1 times
...
Hanbyul
1 year, 5 months ago
Selected Answer: D
D. Document the new risks in the project benefits management plan and risk management plan.
upvoted 1 times
...
kevzzz
1 year, 6 months ago
Selected Answer: D
The issue is a risk
upvoted 1 times
...
Only12go
1 year, 6 months ago
Selected Answer: D
D. Document the new risks in the project benefits management plan and risk management plan.
upvoted 1 times
...
adingmaki
1 year, 7 months ago
D. Anyone who didn't pick D should NOT TAKE THE EXAM.
upvoted 3 times
...
Elle2busy
1 year, 7 months ago
This is scary...has anyone written the exam and used only the answers provided by Exam topics and passed?
upvoted 2 times
adingmaki
1 year, 7 months ago
This site just updates the questions but not answers. Some questions are common sense. But you will still see some people actually voting on the incorrect answer. relying only here and chat GPT
upvoted 2 times
...
...
ParthaPinku
1 year, 7 months ago
Document new risks in Risk management plan?
upvoted 1 times
...
AngelVii
1 year, 7 months ago
Selected Answer: D
I choose D
upvoted 1 times
...
SynikalDemon
1 year, 8 months ago
Selected Answer: D
D for sure.
upvoted 1 times
...
Inzaghi78
1 year, 8 months ago
D this is a risk and should be recorded first
upvoted 1 times
...
khaleghi
1 year, 8 months ago
Selected Answer: D
D. Document the new risks in the project benefits management plan and risk management plan.
upvoted 1 times
...
TestNick001
1 year, 8 months ago
should be D - "may threaten"
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago