A team has been working on a project for several months, but the completion date is unclear because the scope is changing frequently as new knowledge is gained. Some deliverables have already been completed, but when new stakeholders join the team, they complain that project outcomes are not meeting business goals.
How can the project manager prevent this situation from happening in the future?

  • A. Create a prioritized backlog and define iteration review sessions with stakeholders
  • B. Create a detailed work breakdown structure (WBS) and milestone schedule approved by all stakeholders
  • C. Schedule a daily meeting to review team performance and impediments
  • D. Schedule a kick-off meeting for every project phase to share the project management plan with all stakeholders
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Pmpjune152024
Highly Voted 11 months, 2 weeks ago
predictive approach= WBS breakdown structure Changing scope = Agile = prioritize backlog = Answer A
upvoted 5 times
Kim222
8 months, 2 weeks ago
clear!!
upvoted 1 times
...
...
0d83051
Most Recent 1 year ago
Selected Answer: A
The project manager should choose option A. Create a prioritized backlog and define iteration review sessions with stakeholders. In a project where the scope is frequently changing due to new knowledge, it’s important to have a flexible and iterative approach. Creating a prioritized backlog allows the team to focus on the most important tasks first. Regular iteration review sessions with stakeholders ensure that everyone is aligned on the project’s progress and any changes to the scope. This approach allows for continuous feedback and adjustment, which can help prevent misunderstandings and ensure that the project outcomes meet business goals. Remember, the goal of project management is to deliver value to the stakeholders, and this approach helps ensure that the project is always aligned with their needs and expectations. It’s not just about scheduling meetings or creating detailed plans, but about creating a flexible and responsive project management process.
upvoted 2 times
...
d482858
1 year ago
And is A. The completion date is unclear and scope keeps changing so it means it’s an agile approach.
upvoted 1 times
...
dapper18
1 year, 4 months ago
A- as you cannoyt change scope in predicted
upvoted 1 times
...
xcjxcj
1 year, 4 months ago
Selected Answer: B
Iteration is not mentioned, "deliveable completed" indiactes predictive project.
upvoted 3 times
...
reaganFF
1 year, 4 months ago
Nothing in the question indicates that this is an agile project; rather, discussion of 'scope' and 'deliverables' lead one to believe this is a predictive project. IN that case, B - Create a detailed WBS and milestones - would be the most correct answer.
upvoted 1 times
iuedeme
1 year, 1 month ago
Scope can only change in an agile project
upvoted 1 times
Jordarlu
3 months ago
scope creep might happen on either predictive and adaptive method as I learn
upvoted 1 times
Jordarlu
3 months ago
I think the word implying it is using Agile is "Some deliverables have already been completed" becoz the waterfall generates all deliverables only at the end of the project.
upvoted 1 times
...
...
...
...
1234abcdefgh
1 year, 7 months ago
Selected Answer: A
A. Create a prioritized backlog and define iteration review sessions with stakeholders
upvoted 3 times
...
kayyaly
1 year, 8 months ago
Selected Answer: B
B. Create a detailed work breakdown structure (WBS) and milestone schedule approved by all stakeholders
upvoted 3 times
...
victory108
1 year, 8 months ago
Selected Answer: A
A. Create a prioritized backlog and define iteration review sessions with stakeholders
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago