A member of the board of directors has asked the project manager for the estimated cost of the minimum viable product (MVP). The estimated cost is needed in order to get formal approval for this project.
How should the project manager report this cost?
Anssoo
4 days, 22 hours agobuvana
1 year, 1 month agoAbdelmonm
1 year, 3 months agodinodragon
10 months, 2 weeks agommhawish
1 year, 2 months agokevzzz
1 year, 3 months agochlaithem
1 year, 3 months agoUppersquareCapital
1 year, 3 months agoodylec
1 year, 4 months agocb4a6c4
1 year, 4 months agocb4a6c4
1 year, 4 months agosk8chick68
1 year, 5 months agoChezQW
1 year, 6 months agoOnly12go
1 year, 6 months agovictory108
1 year, 6 months agoadingmaki
1 year, 6 months agoadingmaki
1 year, 6 months agosudersonfernando
1 year, 7 months agoMHONK
1 year, 8 months agommhawish
1 year, 2 months ago