Exam PMP topic 1 question 831 discussion

Actual exam question from PMI's PMP
Question #: 831
Topic #: 1
[All PMP Questions]

A project manager works in a startup company and is in charge of a key project that has critical and time-sensitive delivery objectives. One of the project team members missed completing an assigned deliverable on time, despite repeated assurances from the team member that it would be completed on time.

What should the project manager do next?

  • A. Meet with the team member and work on a development plan for them to avoid missed deliverables in the future.
  • B. Hold a team meeting to discuss team member commitments and communications.
  • C. Record the issue, then refocus the team’s efforts on delivering the next set of deliverables.
  • D. Give the team member a formal warning for the negative impact due to failure to deliver and not meet deadlines.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
UppersquareCapital
1 week, 5 days ago
Selected Answer: C
I really don't understand the argument that A is proactive while C is reactive. The question clearly says 'what should the PM do next?'. The project has a critical and time-sensitive deadline and in my opinion the answer should be C.
upvoted 1 times
...
nilopo
1 month, 2 weeks ago
Selected Answer: A
Option A is a proactive approach and good for future delivery due to key project that has critical and time-sensitive delivery objectives. Option C is a reactive approach, hence does not see to be a good one.
upvoted 2 times
...
hoomz
2 months, 2 weeks ago
Selected Answer: C
The project has a critical and time-sensitive deadline. Prolonged focus on the missed deliverable jeopardizes future tasks and the overall project success.
upvoted 1 times
...
chlaithem
3 months, 3 weeks ago
Selected Answer: A
This option emphasizes individual attention, understanding, and proactive solutions. By meeting with the team member: You can discuss the missed deadline, its impact on the project, and the reasons behind it. You can jointly identify any underlying challenges or obstacles faced by the team member, such as workload, knowledge gaps, or resource limitations. You can collaboratively develop a personalized action plan with clear steps and support mechanisms to prevent similar occurrences in the future.
upvoted 1 times
...
odylec
4 months, 1 week ago
Selected Answer: A
A is the answer. You must work with the team member
upvoted 1 times
...
[Removed]
5 months, 3 weeks ago
Selected Answer: A
should be A
upvoted 1 times
...
Only12go
6 months, 2 weeks ago
Selected Answer: A
In this situation, the project manager should take a constructive approach to address the issue: A. Meet with the team member and work on a development plan for them to avoid missed deliverables in the future. It's essential to understand the reasons behind the missed deliverable and work collaboratively with the team member to develop a plan for improvement. This approach focuses on helping the team member address any challenges or obstacles they may be facing and aims to prevent future issues without resorting to formal warnings. Open communication and coaching can often lead to better outcomes and improved performance within the team.
upvoted 3 times
...
Hilary95
6 months, 3 weeks ago
Selected Answer: B
B. Hold a team meeting to discuss team member commitments and communications.
upvoted 2 times
...
nemm235
6 months, 3 weeks ago
Selected Answer: C
C. Record the issue, then refocus the team’s efforts on delivering the next set of deliverables.
upvoted 1 times
...
victory108
6 months, 4 weeks ago
Selected Answer: C
C. Record the issue, then refocus the team’s efforts on delivering the next set of deliverables
upvoted 1 times
...
SynikalDemon
8 months ago
A seems like the real world answer, but B seems like the test answer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.