Exam PMP topic 1 question 813 discussion

Actual exam question from PMI's PMP
Question #: 813
Topic #: 1
[All PMP Questions]

A project's planning phase has just been completed and was defined by team members in remote sessions. The day after the kick-off meeting, which was held at the client facilities, team member A asked the project manager to be moved to another project because they were uncomfortable around team member B.

What should the project manager do to deal with this situation? (Choose two.)

  • A. Speak with both members to try to resolve the situation.
  • B. Transfer team member A to another project.
  • C. Clarify the inclusive practices for project team members.
  • D. Escalate the situation to the project sponsor.
  • E. Transfer team member B to another project.
Show Suggested Answer Hide Answer
Suggested Answer: AC 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
6 months, 3 weeks ago
Selected Answer: AC
A. Speak with both members to try to resolve the situation C. Clarify the inclusive practices for project team members
upvoted 2 times
...
SynikalDemon
8 months ago
Selected Answer: AC
Pretty clearly A and C. You aren't moving either team member, and the project sponsor doesn't need to be involved.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago