Project A is critical for the company and must be completed within nine months. The project charter has been signed but the project scope statement has not been prepared. Management asks the project manager to move forward with the project without an approved project scope statement.
What should the project manager do next?

  • A. Escalate the issue to the project sponsor and add it to the risk register
  • B. Refuse to work on the project because management is not following standard project management practices
  • C. Meet with management to explain the potential problems with running a project without a project scope statement
  • D. Start the project with inputs from the project charter to save time
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
DavidTri
10 months, 2 weeks ago
Selected Answer: C
Firstly, PM need explain the risk to management to understand. If it not resolve then raise the problem to sponsor
upvoted 1 times
...
victory108
1 year, 8 months ago
Selected Answer: C
C. Meet with management to explain the potential problems with running a project without a project scope statement
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...