Question #: 797
Topic #: 1
[All PMP Questions]

As a project is ending, a business stakeholder requests information from the project manager regarding overall project performance to determine the success of the initiative. What should the project manager do to provide relevant information to the stakeholder?

  • A. Update the project status report to include current performance information.
  • B. Document the key performance indicators (KPIs) in the final project report.
  • C. Document the project performance and influencing factors in the lessons learned register.
  • D. Inform the stakeholder that performance will be evaluated three months after project closure.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
chlaithem
1 year ago
Selected Answer: B
Document the key performance indicators (KPIs) in the final project report (most voted): This option focuses on presenting key quantitative data for assessing project success against pre-defined goals. By including relevant KPIs in the final report, the project manager: Provides direct and easily understandable metrics for performance evaluation. Allows the stakeholder to compare actual outcomes to established targets. Demonstrates transparency and accountability for project results.
upvoted 1 times
...
Only12go
1 year, 3 months ago
Selected Answer: B
B. Document the key performance indicators (KPIs) in the final project report. Providing key performance indicators (KPIs) in the final project report is a common and effective way to communicate relevant information about project performance to stakeholders. KPIs provide a concise and quantifiable summary of how the project has performed against its objectives and success criteria. This allows stakeholders to quickly assess the project's overall performance and success. Additionally, the final project report can include other relevant information and insights to provide a comprehensive view of the project's outcomes and lessons learned.
upvoted 1 times
...
victory108
1 year, 3 months ago
Selected Answer: B
B. Document the key performance indicators (KPIs) in the final project report
upvoted 1 times
...
RISHAB1234
1 year, 4 months ago
Option C, documenting the project performance and influencing factors in the lessons learned register, provides a more comprehensive view of the project's overall performance and the factors that contributed to it. This information can be valuable for both the stakeholder and future projects.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...