A project manager identified a risk on a deliverable completed by a contractor and added it to the risk register. During the last inspection meeting for the deliverable, the project manager notices that the suggested mitigation did not produce the expected results.
How should the project manager proceed?
Suldan
1 week ago[Removed]
8 months agoAbdelmonm
9 months agojosephsafiran
9 months, 1 week agochlaithem
9 months, 3 weeks agoloscoe
11 months agoOnly12go
1 year agovictory108
1 year agokayyaly
1 year, 1 month ago