Exam PMI-RMP topic 1 question 154 discussion

Actual exam question from PMI's PMI-RMP
Question #: 154
Topic #: 1
[All PMI-RMP Questions]

The risk manager is currently performing the monitoring and reporting process. Which of the following is an input for schedule metrics?

  • A. Work breakdown structure
  • B. Risk breakdown structure
  • C. Critical path method
  • D. Organizational breakdown structure
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
MikeMarlo
6 months, 3 weeks ago
Selected Answer: A
By analyzing the WBS, project manager can track progress, identify milestones and monitor schedule performance against planned activities. Additionally, it is an output/input, not a tool&technique.
upvoted 1 times
...
JohnSanderson
1 year ago
Critical Path Method is a technique and cannot be an input.
upvoted 2 times
...
OMG4567
1 year, 2 months ago
Selected Answer: C
I agree with Azharmak… C
upvoted 1 times
...
Azharmak
1 year, 2 months ago
I thought it should be Critical Path Method for Schedule.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...