Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PMP topic 1 question 800 discussion

Actual exam question from PMI's PMP
Question #: 800
Topic #: 1
[All PMP Questions]

A project manager is attending a progress meeting with a client. The client requests a design change which might potentially add value to the project.

What action should the project manager take?

  • A. Consult with team members and allow them to make a decision.
  • B. Accommodate the change request to serve the client's needs.
  • C. Convince the client not to make changes to the project.
  • D. Make transactional decisions focusing on the project goals.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
0d83051
1 week, 4 days ago
Selected Answer: A
When a client requests a design change, it’s important for the project manager to consult with the project team before making a decision. The team members, who are working on the project directly, have a better understanding of the project’s scope, timeline, and resources. They can provide valuable insights into the feasibility of the change, its potential impact on the project, and whether it aligns with the project’s objectives.
upvoted 1 times
...
Abdelmonm
3 months ago
Selected Answer: B
The project manager should accommodate the change request to serve the client's needs (Option B). If the client's request has the potential to add value to the project, it aligns with meeting client expectations and satisfaction. However, it's essential for the project manager to carefully assess the impact of the design change on the project scope, schedule, and budget before making any commitments. The decision-making process should involve consulting with relevant team members and stakeholders to ensure that the change is feasible and aligns with the project goals.
upvoted 1 times
...
josephsafiran
3 months, 1 week ago
Selected Answer: B
B. Accommodate the change request to serve the client's needs. Here's why: Client Satisfaction: Meeting the client's needs and accommodating their requests is essential for maintaining a good relationship and ensuring client satisfaction. Adding Value: If the client's requested design change has the potential to add value to the project, accommodating it aligns with the project's objectives of delivering a successful outcome. Communication with Team: While it's important to consult with team members regarding the feasibility and implications of the design change, ultimately, the decision to accommodate the client's request lies with the project manager, considering the overall project goals and client satisfaction.
upvoted 1 times
...
xcjxcj
3 months, 2 weeks ago
Selected Answer: B
A. Team can assess, but no decision B. Let CCB decide C. No change allowed D. I decide, but not final B. makes more sense.
upvoted 2 times
...
Victory007
3 months, 2 weeks ago
Selected Answer: D
This involves carefully evaluating the proposed change and its potential impact on the project's scope, timeline, budget, and quality. The project manager should weigh the potential benefits of the change against the potential costs and risks associated with implementing it.
upvoted 1 times
...
Abdelmonm
3 months, 3 weeks ago
Selected Answer: B
In agile and flexible project environments, accommodating valuable changes that align with the client's needs is often a positive approach. It allows for responsiveness to changing requirements and enhances client satisfaction. However, the decision should be made collaboratively, involving relevant team members and stakeholders. It's important to assess the impact of the change on the project scope, schedule, and budget before making a commitment. If the change adds value and can be accommodated without jeopardizing the project's success, it may be in the project's best interest to proceed with the client's request.
upvoted 1 times
...
chlaithem
3 months, 3 weeks ago
Selected Answer: D
This option emphasizes maintaining project objectives and mitigating risks. By analyzing the change based on project goals and objectives, the project manager ensures compatibility with the overall vision. This includes: Evaluating alignment: Assessing if the suggested change aligns with the project's objectives, target audience, and intended value proposition. Cost-benefit analysis: Weighing the potential benefits of the change against the additional costs, resource demands, and potential delays it might incur. Transparency and communication: Explaining the rationale behind any decision to the client in a transparent and collaborative manner.
upvoted 1 times
...
cb4a6c4
4 months, 1 week ago
Selected Answer: B
Client feels that design change may add value to the project. Review it through a change request.
upvoted 1 times
...
odylec
4 months, 1 week ago
Selected Answer: B
B is the answer. the change add value to the product so you must follow clients needs
upvoted 1 times
...
Jaya12
4 months, 3 weeks ago
Selected Answer: D
Transactional decisions in this context refer to decisions made based on the project's objectives, alignment with the project scope, and potential impact on the project's success criteria. When a client requests a design change that may add value to the project, the project manager should assess the implications of the change on project goals, timeline, budget, and overall success.
upvoted 1 times
...
kevzzz
6 months, 1 week ago
Selected Answer: D
“transactional decision” means any decision taken by a consumer, whether it is to act or to refrain from acting. Project managers should make decisions that align with the project's goals, objectives, and success criteria. If a client proposes a design change that could add value to the project, the project manager should assess the potential impact on the project's scope, schedule, budget, and other constraints. Afterwards, the PM can consult with the team for validation.
upvoted 3 times
...
Uncle_Lucifer
6 months, 1 week ago
Selected Answer: A
consult with team for validation of the clients input and idea.
upvoted 1 times
Uncle_Lucifer
6 months, 1 week ago
Change to B. Its the clients program/project. He/She has the right to have what they like whether good or bad
upvoted 2 times
...
...
ChezQW
6 months, 2 weeks ago
Selected Answer: B
Accommodating the change request would allow for an evaluation of the change before sending it to the change control board. I do not think the PM can make these decisions unilaterally.
upvoted 3 times
...
Only12go
6 months, 2 weeks ago
Selected Answer: A
Its a bad question.. FIrst you would consult with team but not let them necessarily make the descision, we cannot accomadate every potential valuable request from a client becuase we serve them, bad question. but id go with A, then B A. Consult with team members and allow them to make a decision. When a client requests a change, especially one that might add value to the project, it's important to evaluate its potential impact on the project's scope, timeline, cost, and resources. The project manager should consult with team members who have technical and domain expertise to understand the implications of the change. Based on this consultation, a decision can be made on how to proceed, taking into account the project's constraints and goals.
upvoted 1 times
...
Sumbo
6 months, 4 weeks ago
Selected Answer: D
D. Make transactional decisions focusing on the project goals. Explanation: Project managers should make decisions that align with the project's goals, objectives, and success criteria. If a client proposes a design change that could add value to the project, the project manager should assess the potential impact on the project's scope, schedule, budget, and other constraints. If the change aligns with the project goals and objectives and doesn't introduce significant risks or issues, accommodating the change may be a viable option. However, it's essential to follow the project's change control process, evaluate the implications, and obtain the necessary approvals before implementing the change.
upvoted 2 times
...
balaramch
6 months, 4 weeks ago
Selected Answer: B
cant ignore the client request directly, let the CCB decide on the change if really valid.
upvoted 3 times
...
victory108
7 months ago
Selected Answer: A
A. Consult with team members and allow them to make a decision
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...