exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 23 discussion

Actual exam question from PMI's PMI-RMP
Question #: 23
Topic #: 1
[All PMI-RMP Questions]

The project manager generates a monthly risk report for key stakeholders which documents high and medium risk items only. Where would the project manager find the list of recipients for the report?

  • A. Communications management plan
  • B. Risk management plan
  • C. Risk register
  • D. Project charter
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AKB968
1 year, 1 month ago
Risk management plan consists of risk statement, RBS, defination of threats and opportunities, P &I matrix, And Risk Register contains list of identified risk, qualitative and quantitative analysis, risk response planning, risk owner names. AND Project charter is only used for planning in begining, so the correct answer is communication plan. hope it clears.
upvoted 1 times
...
Lunk
1 year, 4 months ago
Careful on this type of question. It is reaching back to PMP materials here.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...