Question #: 164
Topic #: 1
[All PMI-RMP Questions]

The risk manager is documenting the results of the Monitor Risks process to add them to the lessons learned database.
A ) Effectiveness of risk response
B ) Unexpected or undocumented risks which occur

C ) Relevant risk data -

D ) Management reserve report -
Which of the following should be included?

  • A. A, B, C
  • B. A, C, D
  • C. B, C, D
  • D. A, B, D
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Lunk
7 months, 1 week ago
Could someone explain what this question is asking in relation to the possible answers?
upvoted 1 times
OMG4567
7 months, 1 week ago
The question is asking for information which could help a future project. And everything does except the management reserves report.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago