A risk manager on an infrastructure project gathers and analyzes performance data. The risk manager wants to identify which variables will impact the schedule and determine how these factors interact.

Which data analysis tool should the risk manager use to forecast future performance?

  • A. Regression analysis
  • B. What-if scenario analysis
  • C. Sensitivity analysis
  • D. Decision tree analysis
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
2249666
3 months ago
Selected Answer: A
I Think Regression Analysis Purpose: Identifies relationships between variables and how one or more independent variables affect a dependent variable (e.g., schedule performance). Use Case: Used when there is quantitative historical or performance data, and you want to predict outcomes based on how variables behave together. Example: Analyzing how crew size, weather delays, and equipment availability affect project duration.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...