exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 597 discussion

Actual exam question from PMI's PMP
Question #: 597
Topic #: 1
[All PMP Questions]

A multinational company has a plan to expand their business into a new country where they currently have no presence. A project manager is assigned to initiate this project.
After reviewing the business case, what should be considered first when developing an appropriate implementation strategy?

  • A. Acquire project resources from the new country to mitigate the risk of uncertainty
  • B. Evaluate the environmental and regulatory factors and identify high-level risks and assumptions
  • C. Identify and monitor the risks closely since the company does not have lessons learned for this country
  • D. Ensure that project sponsors are in agreement on the project deliverables and timeline during the project
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
1 year, 4 months ago
Selected Answer: B
B. Evaluate the environmental and regulatory factors and identify high-level risks and assumptions
upvoted 1 times
why is it not D. Ensure that project sponsors are in agreement on the project deliverables and timeline during the project? Shouldn't the Business Case have considered the environmental factors, risks and assumptions already?
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...