Exam PMP topic 1 question 602 discussion

Actual exam question from PMI's PMP
Question #: 602
Topic #: 1
[All PMP Questions]

A Scrum team has committed to delivering a specific capability in their first release. Multiple operational issues have prevented the developer from delivering key capabilities. The technical lead has also given notice that they are resigning from the company.
What should the project manager have the Scrum team do to recover from these issues?

  • A. Review constraints in the ongoing sprint planning and evaluate options for the release plan
  • B. Stop the sprint and replan and prioritize the backlog to reduce resource levels
  • C. Consult the resource management plan for an appropriate response
  • D. Continue with existing sprint plans to ensure some of the scope will be delivered
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
DavidTri
10 months, 2 weeks ago
Currrent sprint is still on-going so PM need to review the sprint plan contrain to obtain appropriate solution
upvoted 1 times
...
22d5af5
1 year, 4 months ago
Selected Answer: A
upvoted 1 times
...
victory108
1 year, 8 months ago
Selected Answer: A
A. Review constraints in the ongoing sprint planning and evaluate options for the release plan
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...