exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 627 discussion

Actual exam question from PMI's PMP
Question #: 627
Topic #: 1
[All PMP Questions]

A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement. However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.

What should the project manager do to support the backlog prioritization?

  • A. Support the team to move both items to the next sprint when the team will know more.
  • B. Prioritize the item flagged as high business value and low complexity for this sprint.
  • C. Facilitate the discussion until the team reaches an agreement about the two items.
  • D. Prioritize the item flagged as a dependency with low business value and high complexity.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Syedsaleh28
4 months, 2 weeks ago
Selected Answer: C
Team has to come to consensus for any work they perform, as a PM - his role is to facilitate communication towards and agreement.
upvoted 1 times
...
victory108
7 months, 3 weeks ago
Selected Answer: C
C. Facilitate the discussion until the team reaches an agreement about the two items
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago