exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 138 discussion

Actual exam question from PMI's PMI-RMP
Question #: 138
Topic #: 1
[All PMI-RMP Questions]

A risk manager schedules a project overview meeting with the project sponsor to provide an update on risk management progress. Each functional lead is identifying the most critical information to be presented at an executive level. The information must balance communicating essential information with actions and recommendations.
What risk information should be communicated to the project sponsor?

  • A. Significant risks and issues and their planned responses
  • B. Risk matrix showing the distribution of high, medium, and low risks
  • C. Results of the last project risk brainstorming session
  • D. Summary feedback from the previous risk audit
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
OMG4567
7 months, 1 week ago
Selected Answer: A
Agree… its “Uniform“
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago