Exam PMI-RMP topic 1 question 144 discussion

Actual exam question from PMI's PMI-RMP
Question #: 144
Topic #: 1
[All PMI-RMP Questions]

After years of experience, a project manager becomes the lead manager for a company. This new lead manager asks all project managers to use a specific technique when they perform qualitative risk analysis on their projects. This technique consists of achieving the relative weighting of the project's objectives in terms of priority to the stakeholders.
What is the name of this technique?

  • A. Relative Weighting of the objectives of Stakeholders (RWS)
  • B. Objectives Stakeholders Weighting (OSW)
  • C. Quantitative Weighted Analysis (QWA)
  • D. Analytic Hierarchy Process (AHP)
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
sheraship22
10 months, 2 weeks ago
Selected Answer: D
answer is D: Appendix D, table D3. https://www.pmi.org/-/media/pmi/documents/public/pdf/certifications/practice-standard-project-risk-management.pdf?v=1e0b5985-74af-4c57-963c-b91a9af6fecb
upvoted 1 times
...
OMG4567
1 year, 1 month ago
Selected Answer: D
I think its D
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...