Exam PMP topic 1 question 677 discussion

Actual exam question from PMI's PMP
Question #: 677
Topic #: 1
[All PMP Questions]

An organization is using a hybrid delivery approach for a business project. The product owner, the person who was also managing the project, was promoted to a more senior role. A new project lead has joined the project.

Which artifact should the project lead use to ensure that the project benefits have been identified?

  • A. Statement of work (SOW)
  • B. Business case
  • C. Product backlog
  • D. Solution architecture
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Abdelmonm
9 months ago
Selected Answer: B
The business case is an important artifact that outlines the justification for the project, including its expected benefits. It provides information about why the project is being undertaken and what value it is expected to deliver. When a new project lead joins a project, reviewing the business case can help ensure a clear understanding of the project's objectives and expected benefits.
upvoted 1 times
...
Deeski
10 months, 2 weeks ago
Selected Answer: B
A business case is a value proposition for a proposed project that may included financial and nonfinancial benefits.
upvoted 1 times
...
victory108
1 year, 1 month ago
Selected Answer: B
B. Business case
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago