Actual exam question from PMI's PMP
Question #: 672
Topic #: 1
[All PMP Questions]

A project is starting its sixth iteration out seven. During the daily meeting, a team member explains that a key function will take longer to complete than originally anticipated.

What should the project manager do?

  • A. Ask for help to increase the team capacity to deliver on time.
  • B. Ask for a project extension to deliver the committed scope.
  • C. Update the issue log and escalate the problem to the project sponsor.
  • D. Review the options and possible solutions with the project team.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
7 months ago
Selected Answer: D
D. Review the options and possible solutions with the project team
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago