A project is starting its sixth iteration out seven. During the daily meeting, a team member explains that a key function will take longer to complete than originally anticipated.
What should the project manager do?
A.
Ask for help to increase the team capacity to deliver on time.
B.
Ask for a project extension to deliver the committed scope.
C.
Update the issue log and escalate the problem to the project sponsor.
D.
Review the options and possible solutions with the project team.
D. Review the options and possible solutions with the project team
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
7 months ago