During the early phase of a project, the requirements documentation was not approved. It was identified that the leader of a user party was not included in any of the requirements collection communications.

Which of the documents was likely missed or outdated?

  • A. Stakeholder Register
  • B. Risk Register
  • C. Project Charter
  • D. Business Documentation
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
odylec
11 months, 1 week ago
Selected Answer: A
The Stakeholder Register typically includes information about all project stakeholders, including their roles, interests, and communication requirements. If the leader of a user party was not included in any of the requirements collection communications, it suggests that their information may not have been accurately captured or updated in the Stakeholder Register. Therefore, option A is the most relevant choice in this context.
upvoted 1 times
...
victory108
1 year, 1 month ago
Selected Answer: A
A. Stakeholder Register
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...