A key stakeholder is refusing to participate in a crucial project stage and disagrees with the project team's approach. This situation is affecting the project team's morale.
What should the project manager do?
A.
Ask the project team to meet and document why the stakeholder's approach is incorrect.
B.
Schedule a meeting with the project team and the key stakeholder as soon as possible to discuss and agree on an approach.
C.
Discuss the issue with the project team during a project status meeting and request that they change the approach.
D.
Ask the project sponsor to meet with the project team and key stakeholder to discuss the approach.
I think if one stakeholder disagrees and blocks the project, then this needs to be escalated to the project sponsor - who signed off on the project approach.
B. Schedule a meeting with the project team and the key stakeholder as soon as possible to discuss and agree on an approach
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
odylec
11 months, 1 week ago6thEditionAndy
11 months, 4 weeks agoxcjxcj
10 months, 2 weeks agovictory108
1 year, 1 month ago