A project manager is managing a hybrid project. A stakeholder has directly contacted a team member and has requested a change. Due to the request, the team member was distracted from their work, which caused a loss in productivity
What should the team member do?
victory108
Highly Voted 1 year, 8 months agoAnne99
Most Recent 2 months, 1 week agoAmirov
7 months, 1 week agomengyaoyao
7 months, 3 weeks agoKim222
9 months, 2 weeks agohoomz
1 year, 3 months agojosephsafiran
1 year, 4 months agoBamBT
1 year, 5 months agomesacgon
1 year, 5 months agocb4a6c4
1 year, 6 months agoJaya12
1 year, 6 months agoprinceviper
1 year, 6 months agosudersonfernando
1 year, 8 months ago