A project manager is managing a hybrid project. A stakeholder has directly contacted a team member and has requested a change. Due to the request, the team member was distracted from their work, which caused a loss in productivity
What should the team member do?
victory108
Highly Voted 1 year, 6 months agoAnne99
Most Recent 3 weeks agoAmirov
5 months, 3 weeks agomengyaoyao
6 months agoKim222
8 months agohoomz
1 year, 2 months agojosephsafiran
1 year, 3 months agoBamBT
1 year, 3 months agomesacgon
1 year, 4 months agocb4a6c4
1 year, 4 months agoJaya12
1 year, 4 months agoprinceviper
1 year, 5 months agosudersonfernando
1 year, 7 months ago