exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 712 discussion

Actual exam question from PMI's PMP
Question #: 712
Topic #: 1
[All PMP Questions]

In the middle of an iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeks due to some urgent personal issues. What should the project manager do regarding the activities that were the responsibility of this team member?

  • A. Reach an agreement with the team on how to handle the situation.
  • B. Allow senior management to decide how to proceed with the project.
  • C. Reach out to the procurement team to hire a substitute for the team member.
  • D. Convince the team member not to leave until the project is completed.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
odylec
11 months, 1 week ago
Selected Answer: A
A is the answer. You dont want to add more budget to C.
upvoted 2 times
...
Nassim_Paco
11 months, 2 weeks ago
C. Reach out to the procurement team to hire a substitute for the team member is the correct anwser.
upvoted 1 times
...
Nassim_Paco
11 months, 3 weeks ago
Selected Answer: C
C is the good awnser
upvoted 1 times
...
victory108
1 year, 1 month ago
Selected Answer: A
A. Reach an agreement with the team on how to handle the situation
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...