Actual exam question from PMI's PMP
Question #: 854
Topic #: 1
[All PMP Questions]

A project is nearing completion. The contingency time has been consumed. To ensure that the final deliverables are achieved on time and within budget, the project manager has asked the team to follow a rigorous process. This is causing some resistance among the team members.

What should the project manager do to address the growing resistance?

  • A. Describe to the team members how specific tools and techniques can be used to finish on time.
  • B. Convince team members to use a specific methodology to complete the project on time.
  • C. Crash the project schedule and ask project team members to work overtime to meet the new timeline.
  • D. Motivate project team members by offering incentives to complete the project on time.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Abdelmonm
9 months, 2 weeks ago
Selected Answer: A
Resistance to change is common, especially when a project is nearing completion, and the team has been asked to follow a rigorous process. Providing clear explanations of the tools and techniques, and how they contribute to finishing on time, can address concerns and help team members understand the rationale behind the approach. Communication is key in managing resistance. By explaining the benefits and addressing any misconceptions or fears, the project manager can foster understanding and cooperation among team members.
upvoted 1 times
...
xcjxcj
9 months, 2 weeks ago
Selected Answer: B
Project is late, PM insisted agile, team resisted, what to do? A. Describe agile tool B. Convince agile better C. Let's do overtime D. Bonus for finish on time A or B? To me B better.
upvoted 1 times
...
chlaithem
9 months, 3 weeks ago
Selected Answer: A
This option focuses on transparency, collaboration, and practical solutions. By: Explaining the rationale: Sharing the specific reasons why a more rigorous process is needed in the final stretch provides context and addresses potential concerns about micro-management. Presenting specific tools and techniques: Instead of imposing a fixed methodology, offering a toolbox of practical approaches allows team members to choose methods they are comfortable with and see their immediate value in achieving the deadline. Collaborative problem-solving: Encourage open discussion and invite suggestions from the team on how to streamline processes, optimize workload, and achieve the desired outcom
upvoted 1 times
...
[Removed]
11 months, 3 weeks ago
Selected Answer: A
A is more logical
upvoted 2 times
...
VisuaLHK
12 months ago
Selected Answer: A
go with A
upvoted 3 times
...
Uncle_Lucifer
1 year ago
Selected Answer: A
IT says using rigorous process. --> A D has nothng to do with the requirement
upvoted 2 times
...
kevzzz
1 year ago
Selected Answer: D
Incentives can be other that money and the contingency time is all used up, meaning you don't have time to learn a new tool or technique.
upvoted 1 times
...
David983
1 year ago
Selected Answer: A
I will go with option A. The team have the knowledge, the PM will just address the team on how to use techniques and tools to get susccess. Option D offer incentives just at the end of the project seems like ok 2 years in here with a big effort without incentives but right now when we are in a critical moment I will offer to you something.
upvoted 4 times
David983
1 year ago
Once the team will understand the PM strategic will see clear how can deliver on time and will leave the resistance.
upvoted 1 times
...
...
psvexam
1 year ago
So the answer D is assuming that there is enough money to give incentives, though the contingency time also is consumed. And for A, do they have so much time to learn and adopt to a new tool so late in the game? None of the answers seem to be really accurate.
upvoted 1 times
psvexam
1 year ago
Ans D seems to be the only choice that is close.
upvoted 1 times
...
...
nmw
1 year, 1 month ago
Why not A?
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...