exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 757 discussion

Actual exam question from PMI's PMP
Question #: 757
Topic #: 1
[All PMP Questions]

A project team is conducting sprint planning. Based on the estimated effort, only 95% of the items included in the sprint may be delivered. The product owner asks the project manager for advice on how to prioritize the backlog items.

What should be used to prioritize the backlog items?

  • A. Technical complexity
  • B. Business value
  • C. Risk to delivery
  • D. Estimation accuracy
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
David983
7 months ago
Selected Answer: B
Priorization always based on value and risk
upvoted 1 times
...
Nervys
7 months, 3 weeks ago
b) is the right answer
upvoted 1 times
...
victory108
7 months, 3 weeks ago
Selected Answer: B
B. Business value
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...