Question #: 755
Topic #: 1
[All PMP Questions]

A project has completed design activities ahead of schedule. Suddenly, the project manager is informed by a vendor that a deliverable may not meet the agreed delivery time frame due to a resource shortage. The internal team asked if they should continue to deliver as per the schedule.

What should the project manager do?

  • A. Inform the project team that they may proceed at a more relaxed pace.
  • B. Discuss with the project team alternative options to deliver as planned.
  • C. Inform the project team that some of them will work for the vendor.
  • D. Discuss with the team the need for longer hours to minimize the impact.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
6 months, 4 weeks ago
Selected Answer: B
B. Discuss with the project team alternative options to deliver as planned
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago