A project sponsor receives project information and updates in a timely manner, but the sponsor is concerned because key information is missing in the reports. What should the project manager do?

  • A. Confirm that the project information is understood and feedback is received.
  • B. Determine communication methods, frequency, and level of detail.
  • C. Review the communication needs of key stakeholders.
  • D. Provide all project information to the stakeholder.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Only12go
7 months ago
Selected Answer: C
C. Review the communication needs of key stakeholders. In this scenario, the project sponsor, a key stakeholder, has expressed concerns about missing information in the reports. The project manager should review and reassess the communication needs of the project sponsor and other key stakeholders to ensure that they receive the right information at the right level of detail. Adjusting the content of the reports based on stakeholder needs will ensure that everyone is informed and aligned with the project's progress.
upvoted 1 times
...
victory108
7 months, 2 weeks ago
Selected Answer: C
C. Review the communication needs of key stakeholders
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...