A project manager is working on a hybrid project that has been in progress for the last nine months. Some project stakeholders are becoming frustrated because they do not see the value added by the project.

What should the project manager do to demonstrate the project value?

  • A. Invite the stakeholders to the next sprint review meeting and review the completed work.
  • B. Produce an extensive report highlighting the project's accomplishments.
  • C. Ensure that stakeholders are aware of the current process challenges on the project retrospective.
  • D. Add resources to the project so all of the iterations will be completed earlier.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Victory007
10 months, 1 week ago
Selected Answer: A
This will provide the stakeholders with a firsthand view of the project’s progress and the value it is delivering. It also offers an opportunity for stakeholders to provide feedback and ask questions, which can help address their concerns and improve their understanding of the project’s value.
upvoted 1 times
...
victory108
1 year, 1 month ago
Selected Answer: A
A. Invite the stakeholders to the next sprint review meeting and review the completed work
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...