A project manager writes to the receiving organization to inform them that all acceptance activities are completed with success and it’s time to initiate handover. The receiving manager replies that the team will not be ready for the handover procedure for another two weeks.
What should the project manager do?
ompk
6 months agojosephsafiran
8 months, 3 weeks agoxcjxcj
10 months agoxcjxcj
10 months agoAbdelmonm
10 months agoAbdelmonm
9 months, 2 weeks agochlaithem
10 months, 1 week agoodylec
10 months, 3 weeks agocertificate988
11 months, 3 weeks agopriybas
1 year agokevzzz
1 year agoDavid983
1 year agoOnly12go
1 year agovictory108
1 year, 1 month agovictory108
4 months, 3 weeks agoAymanAbdin
1 year, 1 month agoAymanAbdin
1 year, 1 month ago