Actual exam question from PMI's PMP
Question #: 820
Topic #: 1
[All PMP Questions]

The customer is reviewing the new reporting system and informs the project manager that one of the components in the printing module is not complete.
The project manager reviews the work breakdown structure (WBS) and confirms that the component is included.

What does the project manager need to do first?

  • A. Ask the project team to conduct a quality audit of the printing module components.
  • B. Meet with the project team to understand the issue and define actions.
  • C. Escalate this issue to the project sponsor immediately.
  • D. Raise a change request to immediately implement the printing module component.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
6 months, 3 weeks ago
Selected Answer: B
B. Meet with the project team to understand the issue and define actions
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.