In a standup meeting, a team member has been providing the same update for five consecutive days. The task, which is on the critical path, is now at risk for delaying the schedule.
What should the project manager do?
A.
Keep the project sponsor informed about the delay.
B.
Reassign the task to another member of the team.
C.
Support the team member by providing one more resource to complete the task immediately.
D.
Ask the team member if there is an impediment, and help to remove the blockers.
D. Ask the team member if there is an impediment, and help to remove the blockers
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
6 months, 3 weeks ago