A project is being executed in multiple phases. Midway through, the customer wants to bring in a new tool to replace the existing software in the project as part of their improvement program. The project team has identified the changes and submitted the change request to the customer for approval
What should the project manager do next?
STAR666
3 months, 1 week agod370e49
8 months, 1 week agoKim222
9 months, 1 week agoUppersquareCapital
12 months agoLNX_RM_Admin
1 year agojosephsafiran
1 year, 3 months agoAbdelmonm
1 year, 3 months ago6thEditionAndy
1 year, 5 months agoUncle_Lucifer
1 year, 6 months agokevzzz
1 year, 6 months agosk8chick68
1 year, 6 months agopsvexam
1 year, 7 months agoprokat_mashin_na_vicecity
1 year, 7 months agoUncle_Lucifer
1 year, 6 months agoSumbo
1 year, 7 months agoUncle_Lucifer
1 year, 6 months ago