Exam PMP topic 1 question 827 discussion

Actual exam question from PMI's PMP
Question #: 827
Topic #: 1
[All PMP Questions]

A project manager is assigned to lead an enterprise transformation to address change and value delivery at the organizational level. The project manager is working with the team to deliver incremental changes.

What should the project manager do to ensure the success of this endeavor at both the team and organizational levels?

  • A. Get buy-in from senior management to enforce adoption of the organizational enterprise transformation.
  • B. Analyze the impact of changes and risk associated with deliveries on a continuous basis.
  • C. Involve governance on establishing trust and transparency to aid the transformation journey.
  • D. Coordinate with the functional managers and get their buy-in as early as possible to avoid resistance.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Only12go
6 months, 3 weeks ago
Selected Answer: B
Option B, "Analyze the impact of changes and risk associated with deliveries on a continuous basis," takes a comprehensive approach. By continuously analyzing the impact of changes and associated risks, the project manager ensures that the transformation is adaptable and responsive to emerging challenges or opportunities. This is crucial in an enterprise transformation where the environment can be dynamic, and the organization needs to be agile in its response.
upvoted 1 times
...
slick90
7 months ago
Selected Answer: B
B. You need continuous assessment
upvoted 1 times
...
victory108
7 months, 1 week ago
Selected Answer: B
B. Analyze the impact of changes and risk associated with deliveries on a continuous basis
upvoted 1 times
victory108
4 months, 3 weeks ago
C. Involve governance on establishing trust and transparency to aid the transformation journey
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.