Sprint size, which refers to the amount of work committed to and completed during an iteration, is a crucial factor in Agile projects.
If the team consistently misses planned user stories, it may indicate that the sprint size is too large for the iteration duration.
The project manager should assess and adjust the sprint size to better align with the team's capacity and improve the likelihood of meeting commitments.
Adjusting the sprint size allows for a more realistic and achievable workload, promoting successful completion of user stories within each iteration.
A. Ensure the sprint size is appropriate for the iteration duration
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Abdelmonm
11 months, 3 weeks agovictory108
1 year, 3 months ago