Exam PMP topic 1 question 822 discussion

Actual exam question from PMI's PMP
Question #: 822
Topic #: 1
[All PMP Questions]

A project manager is managing a project aimed at providing incremental deliveries to the market every three months. The team has been assigned, and the product backlog was created and prioritized by the product owner. After four iterations, the product owner escalates complaints to the CEO because the product does not meet the product owner's expectations.

What should the project manager have done to prevent this situation from happening?

  • A. Reviewed the organizational process assets (OPAs) and lessons learned from similar projects
  • B. Performed risk management analysis during daily scrums
  • C. Performed backlog grooming to ensure that acceptance criteria were being met
  • D. Implemented sprint reviews with the product owner and retrospectives with the team to minimize gaps
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Abdelmonm
9 months ago
Selected Answer: D
Sprint reviews involve reviewing the increment of work and adapting the product backlog based on feedback. Retrospectives are sessions held at the end of each sprint to reflect on what went well and what could be improved. By implementing sprint reviews and retrospectives, the project manager can identify and address gaps or issues early in the project, preventing escalation of complaints later on. Continuous communication and collaboration with the product owner during these sessions help ensure that expectations are aligned and met.
upvoted 2 times
...
kevzzz
9 months, 2 weeks ago
Selected Answer: D
A sprint review is a collaborative meeting that is typically held at the end of every sprint. This is when the team runs through work items they completed during the sprint or iteration. A sprint review ensures key stakeholders are up to date, and it enables them to provide feedback.
upvoted 1 times
...
victory108
1 year ago
Selected Answer: D
D. Implemented sprint reviews with the product owner and retrospectives with the team to minimize gaps
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago