Exam PMP topic 1 question 838 discussion

Actual exam question from PMI's PMP
Question #: 838
Topic #: 1
[All PMP Questions]

One of the modules delivered by the project failed during user acceptance testing (UAT). The project manager realizes that the component that failed the functional tests was created by another team and a different functionality was approved by the business manager.

What should the project manager do?

  • A. Review the integrated change control process with all the stakeholders.
  • B. Escalate the misalignment to the project management office (PMO) and the functional manager's director.
  • C. Ask the project management office (PMO) to recover the cost of fixing it from the other team's budget.
  • D. Request dedicated business resources to support functional testing.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Anssoo
4 days, 22 hours ago
Selected Answer: B
B. If we selec A, what should be discussed in the meeting? None!
upvoted 1 times
...
UppersquareCapital
5 months, 1 week ago
Selected Answer: A
Identify the Root Cause: The failure of the module during UAT and the misalignment in approved functionality indicate that there may have been issues with communication, documentation, or adherence to change control processes. Reviewing the integrated change control process will help identify where the misalignment occurred and why the incorrect functionality was approved. Ensure Compliance: The integrated change control process is designed to ensure that all changes to the project are properly reviewed, approved, documented, and communicated to all relevant stakeholders. By reviewing this process with all stakeholders, the project manager can ensure that everyone understands and follows the proper procedures, thereby preventing similar issues in the future. Engaging all stakeholders in the review process can improve communication and collaboration among teams. It helps ensure that everyone is on the same page and that any changes are accurately reflected in the project deliverables.
upvoted 2 times
...
Abdelmonm
9 months, 2 weeks ago
Selected Answer: B
In this situation, where a component created by another team failed functional tests and a different functionality was approved by the business manager, it's essential to escalate the misalignment to the appropriate authorities. The project manager should involve the project management office (PMO) and the director of the functional manager to address the issue. Escalating the matter ensures that it receives the attention and resolution it needs at a higher level in the organization. It's important to involve key stakeholders to address the misalignment and take corrective actions.
upvoted 2 times
UppersquareCapital
5 months, 1 week ago
While escalation might be necessary if there are persistent issues, the immediate need is to address the root cause and prevent recurrence. Escalation without understanding the process breakdown may not resolve the underlying issue. Therefore, the most appropriate action for the project manager is to review the integrated change control process with all the stakeholders.
upvoted 1 times
...
...
victory108
1 year ago
Selected Answer: A
A. Review the integrated change control process with all the stakeholders
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel