exam questions

Exam CAPM All Questions

View all questions & answers for the CAPM exam

Exam CAPM topic 1 question 282 discussion

Actual exam question from PMI's CAPM
Question #: 282
Topic #: 1
[All CAPM Questions]

Due to organizational changes, a new product owner joins a project. The product owner wants to review the process used to obtain team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work.

What process should the project manager review with the product owner?

  • A. Acquire Resources
  • B. Plan Resource Management
  • C. Estimate Activity Resources
  • D. Control Resources
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
JesseChou_123
3 weeks, 6 days ago
Selected Answer: A
Why the other options are incorrect: B. Plan Resource Management: This is about developing the strategy for managing resources — not the actual process of obtaining them. C. Estimate Activity Resources: This step involves estimating the types and quantities of resources needed, but not acquiring them. D. Control Resources: This process is about monitoring and managing resources after they have been acquired — not how they were obtained.
upvoted 1 times
...
JesseChou_123
1 month, 2 weeks ago
Selected Answer: A
Breakdown of Other Options: B. Plan Resource Management: This is where you define how to estimate, acquire, manage, and use resources — a planning activity, not where actual acquisition happens. C. Estimate Activity Resources: This process is for determining what resources (and how much of each) will be needed — it's about estimation, not acquisition. D. Control Resources: This involves monitoring and adjusting resource use — managing resources during the project, not the process of obtaining them.
upvoted 1 times
...
8a6d137
4 months ago
Selected Answer: A
PMBOK v6; section 9.3 Acquire Resources: The process of obtaining team members, facilities, equipment, materials, supplies, and other resources necessary to complete project work.
upvoted 2 times
...
Vangelis_1980
1 year ago
Selected Answer: A
A. Acquire Resources Explanation: The Acquire Resources process specifically focuses on obtaining the necessary team members, facilities, equipment, materials, supplies, and other resources for project execution. This process aligns directly with the product owner's inquiry about how the project obtains these essential components.
upvoted 1 times
...
Andrew_1980
1 year ago
Selected Answer: B
Reviewing the plan created earlier
upvoted 1 times
...
shubu2276
1 year, 6 months ago
Selected Answer: B
In this scenario, since the new product owner wants to review the process related to obtaining resources, the project manager should review the "Plan Resource Management" process with the product owner.
upvoted 1 times
...
HPouria
1 year, 9 months ago
Selected Answer: A
The Acquire Resources process is part of the Project Resource Management knowledge area, and it focuses on obtaining the resources required to complete the project work. This process involves identifying, acquiring, and managing the resources needed for project activities. Reviewing this process with the new product owner can help ensure that the project team has the necessary resources to deliver the project successfully.
upvoted 1 times
...
jesslhong
1 year, 9 months ago
I would think A is the more specific/appropriate answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...