A project team is reviewing the project business document for a phase-gate session and discovers that the benefits need to be validated by the project sponsor.
Unfortunately, the project sponsor was recently changed, and the new sponsor does not seem to be supportive.
What should the project manager do to address this situation?
David8989
Highly Voted 1 year, 5 months agofunmis4
Most Recent 7 months, 1 week agoKim222
8 months, 3 weeks ago0d83051
1 year agoAshPik
1 year, 1 month agoTrytrio
1 year, 2 months agojosephsafiran
1 year, 3 months agoAbdelmonm
1 year, 3 months agoloscoe
1 year, 5 months agoUncle_Lucifer
1 year, 5 months agoDavid983
1 year, 6 months ago