A project team is reviewing the project business document for a phase-gate session and discovers that the benefits need to be validated by the project sponsor.
Unfortunately, the project sponsor was recently changed, and the new sponsor does not seem to be supportive.
What should the project manager do to address this situation?
0d83051
1 week, 4 days agoAshPik
1 month, 2 weeks agoTrytrio
3 months agojosephsafiran
3 months, 1 week agoAbdelmonm
3 months, 2 weeks agoloscoe
5 months, 1 week agoUncle_Lucifer
6 months agoDavid8989
6 months agoDavid983
6 months, 2 weeks ago