A. An updated risk register
Explanation:
A risk register is a central repository for documenting all identified project risks. It includes details such as:
Risk description
Risk probability
Risk impact
Risk owner
Risk response plan
B. Risk breakdown structure
The Risk Breakdown Structure (RBS) is a tool that a project manager can use to deal with multiple sources of risk. It is a hierarchical decomposition of risks that helps identify, categorize, and understand the various sources of risk in a project. By breaking down risks into smaller components or categories, the project manager can systematically analyze and address each area of concern. The RBS is an essential tool in risk management and can be used in conjunction with other tools, such as the risk register, to effectively manage and mitigate risks throughout the project lifecycle.
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Vangelis_1980
9 months agoshubu2276
1 year, 3 months agolifelong_learner
1 year, 6 months ago