The project manager has asked for the P50 estimate for the project schedule. What is the P50 estimate?

  • A. 75 days
  • B. 73.5 days
  • C. 73 days
  • D. 72.5 days
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AKB968
1 year, 1 month ago
one of easist questions C
upvoted 1 times
...
Azharmak
1 year, 3 months ago
C is the answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...