During the initiation phase, a sponsor recommends that all team members should be colocated. Some of the team members need a significant amount of time to commute, and there is no office space available.

What should the project manager do?

  • A. Log this as a risk, since colocating the team will require additional costs.
  • B. Colocate the project team because that is what the sponsor requested.
  • C. Assess the business benefits of a colocated project team.
  • D. Colocate the project team because it will increase efficiency.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
6 months, 2 weeks ago
Selected Answer: C
C. Assess the business benefits of a colocated project team
upvoted 1 times
...
517f9da
1 year ago
Selected Answer: C
C. Assess the business benefits of a colocated project team. By assessing the business benefits of a colocated project team, the project manager can provide a well-informed recommendation that considers the potential advantages and disadvantages of colocation.
upvoted 1 times
...
buvana
1 year, 6 months ago
C. Assess the business benefits of a colocated project team.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...