During the initiation phase, a sponsor recommends that all team members should be colocated. Some of the team members need a significant amount of time to commute, and there is no office space available.
What should the project manager do?
A.
Log this as a risk, since colocating the team will require additional costs.
B.
Colocate the project team because that is what the sponsor requested.
C.
Assess the business benefits of a colocated project team.
D.
Colocate the project team because it will increase efficiency.
C. Assess the business benefits of a colocated project team.
By assessing the business benefits of a colocated project team, the project manager can provide a well-informed recommendation that considers the potential advantages and disadvantages of colocation.
C. Assess the business benefits of a colocated project team.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.