exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 10 discussion

Actual exam question from PMI's PMI-RMP
Question #: 10
Topic #: 1
[All PMI-RMP Questions]

In the country where a project is being executed, customs procedures are complex and change frequently. During the risk identification process, the project team identifies a risk related to delays in customs on substantial equipment that will likely occur. Equipment delays on this project could lead to the project cancellation.
How should the probability and impact be characterized for this risk?

  • A. Low probability/low impact
  • B. High probability/low impact
  • C. Low probability/high impact
  • D. High probability high impact
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
TheAWSGuru
6 months, 2 weeks ago
D for sure .
upvoted 1 times
...
AKB968
11 months, 1 week ago
D, high probablity with cancellation of project (High impact)
upvoted 1 times
...
Azharmak
11 months, 2 weeks ago
Likely occur is a high probability?
upvoted 1 times
...
Azharmak
12 months ago
D high probability and impact too is high
upvoted 1 times
...
D because this risk will likely occur and lead to the project cancellation! High probability and high impact
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...