A project manager is managing a technical project that requires intensive documentation as part of the key deliverables. In a project review meeting. a key stakeholder reports that the latest documentation provided by the project manager includes a reference to unrelated products.
What should the project manager do?
victory108
7 months, 3 weeks agoUppersquareCapital
1 year, 1 month ago517f9da
1 year, 2 months agoUppersquareCapital
1 year, 6 months agoAbdelmonm
1 year, 6 months agocertificate988
1 year, 7 months agocertificate988
1 year, 7 months agoOneAgent
1 year, 7 months ago